BULK FUELING FACILITY
Client: A Bulk Fueling Facility
Location: Seattle, WA
About the Project
A bulk fueling facility contacted Clear Creek to assist with their stormwater discharges. The staff maintained a good BMP schedule and kept their site clean, but still had issues with elevated metals in their runoff. The facility was targeted by a citizen suit under the Clean Water Act, and had to fast track their solution to meet their consent decree.
The facility reached out to Clear Creek for a fast response. Clear Creek worked with their facility and an outside engineering firm to upgrade their infrastructure and provide a treatment solution with 120 days. Bench testing showed that simple mechanical filtration followed by a polishing adsorptive media lowered all pollutants to non-detect ranges, and a system was designed around this treatment train. Clear Creek trained the facility personnel to conduct routine system maintenance.
Services Provided
- Laboratory Treatability Testing
- Permitting Assistance
- Fast Track Design and Mobilization
- System Design / Build
- System Maintenance & Monitoring
Technology Provided
- Mechanical Filtration
- Polishing Adsorptive Media
- System Automation
- 50 gallons-per-minute
Project Statistics
- 1.2 – Acre Site
- Discharge to Marine Waters
- Target Pollutants: Turbidity, Cu & Zn
- Commissioned in 2016