HEAVY EQUIPMENT PROVIDER
Client: A Heavy Equipment Provider
Location: Tacoma, WA
About the Project
Clear Creek was contacted by a heavy equipment sales and services facility in Tacoma, WA to help solve issues with turbidity and metals. Pressure from a third-party Clean Water Act lawsuit required that treatment equipment be installed and operational within a tight time-frame.
Clear Creek conducted bench testing and determined that a chitosan enhanced sand filtration (CESF) system was capable of meeting all benchmarks. A CESF system was quickly fabricated, delivered, and installed at the facility. Clear Creek went from site evaluation to system commissioning within a 120-day time-frame, allowing the facility to meet the compliance schedule laid out in their settlement.
Services Provided
- In-House Bench Testing
- System and Infrastructure Design
- Water Treatment Plan Submittal
- Fast Track Mobilization
- Long-term O&M Assistance
Technology Provided
- Chitosan Enhanced Sand Filtration
- 200 gallons-per-minute
- Full system automation
Project Statistics
- 4.8 – Acre Site
- Discharge to Surface Waters
- Pollutants: NTU, Cu, Zn
- 100% Compliance